Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
Gen-2006-002 |
January 09, 2006 |
Request to interconnect 150MW on the AEPW system |
Facility Study completed September 2007 |
Download |
GEN-2006-006 |
August 01, 2009 |
Interconnect 205.5 MW to the MKEC transmission system |
Posted 3/11/2010 |
Download |
Gen-2006-008 |
February 27, 2008 |
Request to interconnect 550MW on the AEPW system |
Facility Study completed March 2007 |
Download |
Gen-2006-010 |
February 27, 2006 |
Request to interconnect 620MW on the AEPW system |
Facility Study completed May 2007 |
Download |
Gen-2006-014 |
March 02, 2006 |
Request to interconnect 300MW on the MIPU System |
Facility Study completed July 2007 |
Download |
Gen-2006-015 |
April 24, 2006 |
Request to interconnect 170MW on the SWPS system |
Facility Study completed October 2006 |
Download |
Gen-2006-017 |
June 02, 2006 |
Request to interconnect 300MW on the MIPU system |
Facility Study completed January 2008 |
Download |
Gen-2006-018 |
June 14, 2006 |
Request to interconnect 170MW on the SWPS system |
Facilities Study completed November 2007 |
Download |
Gen-2006-019 |
June 19, 2006 |
Request to interconnect 275MW on the SPRM system |
Facility study completed June 2007 |
Download |
GEN-2006-020s |
June 20, 2006 |
Request to interconnect 18.9 MW on the SWPS system |
Facility Study completed May 2007 |
Download |
Gen-2006-021 |
June 21, 2006 |
Request to interconnect 250MW on the WPEK system |
Facility Study completed October 2007 |
Download |
Gen-2006-022 |
June 21, 2006 |
Request to interconnect 150MW on the WPEK system |
Facility Study completed November 2008 |
Download |
Gen-2006-024S |
July 07, 2006 |
Request to interconnect 19.8 MW on the WFEC system |
Facility Study completed June 2007 |
Download |
Gen-2006-026 |
July 26, 2006 |
Request to interconnect 502MW on the SWPS system |
Facility Study completed March 2007 |
Download |
Gen-2006-027 |
August 11, 2006 |
Request to interconnect 320MW on the WERE system |
Facility Study completed May 2007 |
Download |
Gen-2006-028 |
August 11, 2006 |
Request to interconnect 300MW on the WERE system |
Facility Study completed May 2007 |
Download |
Gen-2006-031 |
August 16, 2006 |
Request to interconnect 75MW o n the MIDW system |
Facility Study completed July 2007 |
Download |
GEN-2006-032 |
August 21, 2006 |
Request to interconnect 210MW on the MIDW system |
Facility Study completed January 2008 |
Download |
Gen-2006-033 |
August 22, 2006 |
Request to interconnect 150MW on the WERE system |
Facility Study completed February 2008 |
Download |
Gen-2006-034 |
August 23, 2006 |
Request to interconnect 81MW on the SUNC system |
Facility Study completed February 2008 |
Download |
Gen-2006-035 |
August 29, 2006 |
Request to interconnect 225MW on the AEPW system |
Facilities Study completed November 2007 |
Download |
Gen-2006-038 |
October 16, 2006 |
Request to interconnect 750MW on the WFEC system |
Facility study completed May 2008 |
Download |
Gen-2006-039 |
October 30, 2006 |
Request to interconnect 400MW on the SWPS system |
Facility Study completed January 2008 |
Download |
Gen-2006-040 |
November 07, 2006 |
Request to interconnect 108 MW on the SUNC System |
Facility Study completed November 2008 |
Download |
Gen-2006-043 |
November 17, 2006 |
Request to interconnect 126MW on the AEPW system |
Facility Study completed June 2008 |
Download |
Gen-2006-044 |
December 04, 2006 |
Request to interconnect 400MW on the SWPS system |
Updated Facility Study completed 1/27/09 |
Download |
Gen-2006-045 |
December 05, 2006 |
Request to interconnect 240MW on the SWPS system |
Facility Study completed February 2008 |
Download |
Gen-2006-046 |
December 05, 2006 |
Request to interconnect 130.2 MW on the OKGE systesm |
Facility Study completed April 2008 |
Download |
Gen-2006-047 |
December 05, 2006 |
Request to interconnect 240MW on the SWPS system |
Facility study completed May 2008 |
Download |
Gen-2006-048 |
December 08, 2006 |
Request to interconnect 150MW on the SWPS system |
Facility Study completed April 2009 |
Download |
Gen-2006-049 |
December 18, 2006 |
Request to interconnect 400MW on the SWPS System |
Study completed June 2009 |
Download |
GEN-2006-049 |
June 06, 2008 |
Request to interconnect 400MW on the SWPS System |
Posted 6/28/2012 |
Download |