2007 Feasibility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
Gen-2007-001 January 19, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed July 2007 Download
Gen-2007-003 January 30, 2007 Request to interconnect 30MW on the SUNC system Feasibility Study completed September 2007 Download
Gen-2007-004 February 01, 2007 Request to interconnect 150MW on the SWPS system Feasibility Study completed July 2007 Download
Gen-2007-005 February 05, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed August 2007 Download
Gen-2007-006 February 14, 2007 Request to interconnect 200MW on the OKGE system Feasibility Study completed August 2007 Download
Gen-2007-008 February 23, 2007 Request to interconnect 300MW on the SWPS system Feasibility Study completed August 2007 Download
Gen-2007-009 February 23, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed August 2007 Download
Gen-2007-010 February 28, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed August 2007 Download
Gen-2007-011 March 09, 2007 Request to interconnect 135MW on the SUNC system Feasibility Study completed September 2007 Download
Gen-2007-012 March 20, 2007 Request to interconnect 300MW on the SUNC system Feasibility Study completed October 2007 Download
Gen-2007-013 March 23, 2007 Request to interconnect 99MW on the SUNC system Feasibility Study completed October 2007 Download
Gen-2007-014 March 27, 2007 Request to interconnect 135MW on the WFEC System Feasibility Study completed October 2007 Download
Gen-2007-015 March 27, 2007 Request to interconnect 135MW on the WERE system Feasibility Study completed November 2007 Download
Gen-2007-017 April 13, 2007 Request to interconnect 100.5MW on the MIPU system Feasibility Study completed February 2008 Download
Gen-2007-018 April 13, 2007 Request to interconnect 315MW on the MIPU system Feasibility Study completed September 2007 Download
Gen-2007-019 April 27, 2007 Request to interconnect 500MW on the SWPS system Feasibility study completed January 2008 Download
Gen-2007-021 May 09, 2007 Request to interconnect 201MW on the OKGE system FB study completed January, 2008 Download
Gen-2007-023 May 18, 2007 Request to interconnect 800MW on t he WERE system Feasibility Study completed November 2007 Download
Gen-2007-024 May 22, 2007 Request to interconnect 120MW on the SWPS system FB study completed January, 2008 Download
Gen-2007-025 May 24, 2007 Request to interconnect 300MW on the WERE system FB study completed January, 2008 Download
Gen-2007-026 May 31, 2007 Request to interconnect 130.2MW on the SWPS system Feasibility Study completed February 2008 Download
Gen-2007-027 June 22, 2007 Request to interconnect 150MW on the SWPS system Feasibility Study completed April 2008 Download
Gen-2007-028 June 29, 2007 Request to interconnect 200MW on the MKEC system Feasibility Study completed December 2007 Download
Gen-2007-029 June 29, 2007 Request to interconnect 200MW on the WFEC system Feasibility Study completed February 2008 Download
Gen-2007-030 July 05, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed April 2008 Download
Gen-2007-032 July 25, 2007 Request to interconnect 150MW on the WFEC system Feasibility Study completed February 2008 Download
Gen-2007-033 August 08, 2007 Request to interconnect 200MW on the SWPS system Feasibility Study completed February 2008 Download
Gen-2007-034 August 16, 2007 Request to interconnect 150MW on the SWPS system Feasibility Study completed February 2008 Download
Gen-2007-035 September 05, 2007 Request to interconnect 100MW on the AEPW System Feasibililty Study completed March 2008 Download
Gen-2007-036 September 14, 2007 Request to interconnect 200MW on the SUNC system Feasibility Study completed March 2008 Download
Gen-2007-037 September 17, 2007 Request to interconnect 200MW on the SUNC system Feasibility Study completed March 2008 Download
Gen-2007-038 September 17, 2007 Request to interconnect 200MW on the SUNC system Feasibility Study completed March 2008 Download
Gen-2007-039 September 17, 2008 Request to interconnect 120MW on the SWPS system Feasibility Study completed April 2008 Download
Gen-2007-040 September 25, 2007 Request to interconnect 500MW on the SUNC system Feasibility Study completed April 2008 Download
Gen-2007-041 September 25, 2007 Request to interconnect 500MW on the SWPS system Feasibility Study completed May 2008 Download
Gen-2007-042 September 28, 2007 Request to interconnect 360MW on the SWPS system. Feasibility Study completed June 2008 Download
Gen-2007-043 October 02, 2007 Request to interconnect 300MW on the AEPW system Feasibility Study completed April 2008 Download
Gen-2007-047 October 17, 2007 Request to interconnect 204MW on the SUNC system Feasibility Study completed June 2008 Download
Gen-2007-049 October 22, 2007 Request to interconnect 75MW on the WFEC system Feasibility Study completed May 2008 Download
Gen-2007-052 November 07, 2007 Request to interconnect 200MW on the WFEC system Feasibility Study completed May 2008 Download
Gen-2007-054 December 03, 2007 Request to interconnect 550MW on the SWPS system Feasibility Study completed June 2008 Download