2006 Feasibility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
Gen-2006-001 January 09, 2006 Request to interconnect 45MW on the WFEC System Feasibility Study completed August 2006 Download
Gen-2006-002 January 09, 2006 Request to interconnect 150MW on the AEPW system Feasibility Study completed August 2006 Download
Gen-2006-003 February 07, 2006 Request to interconnect 50MW on the MIPU System Feasibility Study completed September 2006 Download
Gen-2006-004 February 14, 2006 Request to interconnect 620MW on the AEPW system Feasibility Study completed August 2006 Download
Gen-2006-006 February 16, 2006 Request to interconnect 205.5MW on the WPEK Systesm Feasibililty Study completed Septembe 2006 Download
Gen-2006-008 February 27, 2006 Request to interconnect 550MW on the AEPW system Feasibility Study completed September 2006 Download
Gen-2006-014 March 02, 2006 Request to interconnect 300MW on the MIPU system Feasibility Study completed October 2006 Download
Gen-2006-017 June 02, 2006 Request to interconnect 300MW on the MIPU system Feasibility Study completed November 2006 Download
Gen-2006-020S June 20, 2006 Request to interconnect 18.9MW on the SWPS System Feasibility Study completed September 2006 Download
Gen-2006-021 June 21, 2006 Request to interconnect 250 MW on the WPEK System Feasibility Study completed December 2006 Download
Gen-2006-022 June 21, 2006 Request to interconnect 150MW on the WPEK system Feasibility Study completed December 2006 Download
GEN-2006-024S July 07, 2006 Request to interconnect 19.8 MW on the WFEC system Feasibility Study completed October 2006 Download
Gen-2006-025 July 07, 2006 Request to interconnect 150MW on the SWPS System Feasibility Study completed October 2006 Download
Gen-2006-027 August 11, 2006 Request to interconnect 320MW on the WERE System Feasibility Study completed December 2006 Download
Gen-2006-028 August 11, 2006 Request to interconnect 300MW on the WERE System Feasibility Study completed December 2006 Download
Gen-2006-029 August 11, 2006 Request to interconnect 300MW on the WERE system Feasibility Study completed December 2006 Download
Gen-2006-031 August 16, 2006 Request to interconnect 75MW on the MIDW System Feasibility Study completed January 2007 Download
Gen-2006-033 August 22, 2006 Request to interconnect 150MW on the WERE System Feasibility Study completed January 2007 Download
Gen-2006-034 August 23, 2006 Request to interconnect 81MW on the SUNC system Feasibility Study completed February 2007 Download
Gen-2006-035 August 29, 2006 Request to interconnect 225MW on the AEPW system Feasibility Study completed February 2007 Download
Gen-2006-036 September 13, 2006 Request to interconnect 85.5 MW on the SWPS Feasibility Study completed March 2007 Download
Gen-2006-037 September 15, 2006 Request to interconnect 900MW on the OKGE System Feasibility Study completed January 2007 Download
Gen-2006-038 October 16, 2006 Request to interconnect 750MW on the WFEC system Feasisbility Study completed March 2007 Download
Gen-2006-039 October 30, 2006 Request to interconnect 400 MW on the SWPS system Feasibility Study completed April 2007 Download
Gen-2006-040 November 07, 2006 Request to interconnect 108 MW on the SUNC system Feasibility Study completed April 2007 Download
Gen-2006-041 November 09, 2006 Request to interconnect 19.8 MW on the MIDW system Feasibility Study completed June 2007 Download
Gen-2006-042 November 13, 2006 Request to interconnect 600 MW on the OKGE system Impact Study completed April 2007 Download
Gen-2006-043 November 17, 2006 Request to interconnect 300MW on the AEPW system Feasibility Study completed May 2007 Download
Gen-2006-044 December 04, 2006 Request to interconnect 400MW on the SWPS system Feasibility Study completed June 2007 Download
Gen-2006-045 December 05, 2006 Requests to interconnect 240MW on the SWPS system Feasibility Study completed May 2007 Download
Gen-2006-046 December 05, 2006 Request to interconnect 130.2MW on the OKGE system Feasibility Study completed June 2007 Download
Gen-2006-047 December 05, 2006 Request to interconnect 240MW on the SWPS system Feasibility Study completed June 2007 Download
Gen-2006-048 December 08, 2006 Request to interconnect 150MW on the SWPS system Feasibility Study completed June 2007 Download
Gen-2006-049 December 18, 2006 Request to interconnect 400MW on the SWPS system Feasibility Study completed June 2007 Download
Gen-2007-008 February 23, 2007 Request to interconnect 300MW on the SWPS system Feasibility Study completed August 2007 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.