Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
GEN-2004-001 |
January 06, 2004 |
Request to interconnect up to 200MW on the SWPS system |
***WITHDRAWN*** |
|
GEN-2004-002 |
January 16, 2004 |
Request to interconnect up to 200 MW on the WERE system |
Feasibility Study Completed 9/28/04 ***WITHDRAWN*** |
Download |
GEN-2004-003 |
February 04, 2004 |
Request to interconnect up to 240MW on the SWPS system |
Feasibility Study Completed 12/2004 |
Download |
GEN-2004-004 |
February 04, 2004 |
Request to interconnect up to 240MW on the SWPS system |
***WITHDRAWN*** |
|
GEN-2004-005 |
February 09, 2004 |
Request to interconnect up to 275MW on the SPRM system |
Feasibility Study Completed June 2004 |
Download |
GEN-2004-006 |
March 25, 2004 |
Request to interconnect up to 100MW on the WERE system |
***WITHDRAWN*** |
|
GEN-2004-007 |
March 25, 2004 |
Request to interconnect up to 150MW on the WERE system |
***WITHDRAWN*** |
|
GEN-2004-008 |
March 26, 2004 |
Request to interconnect up to 900MW on the KCPL system |
Expedited Impact Study requested |
|
GEN-2004-009 |
March 30, 2004 |
Request to interconnect up to 80MW on the SWPS system |
Feasibility Study Completed 1/31/05 ***WITHDRAWN*** |
Download |
GEN-2004-010 |
April 07, 2004 |
Request to interconnect up to 300 MW on the WERE System |
Feasibility Study completed 10/19/04 |
Download |
GEN-2004-011 |
April 16, 2004 |
Request to interconnect up to 201MW on the KCPL system |
Feasibility Study completed 12/10/04 ***WITHDRAWN*** |
Download |
GEN-2004-012 |
April 20, 2004 |
Request to interconnect up to 900MW on the KCPL system |
Expedited Impact Study requested |
|
GEN-2004-013 |
April 20, 2004 |
Request to interconnect up to 900MW on the KCPL system |
Expedited Impact Study requested |
|
GEN-2004-014 |
April 22, 2004 |
Request to interconnect up to 154.5MW on the MIDW system |
Feasibility Study Completed 4/12/2005 |
Download |
GEN-2004-015 |
July 12, 2004 |
Request to interconnect up to 170 MW on the SWPS system |
Expedited Impact Study requested |
|
GEN-2004-016 |
July 15, 2004 |
Request to interconnect up to 150 MW on the WERE system |
Fesibility Study Completed April 13, 2005 |
Download |
GEN-2004-017 |
August 23, 2004 |
Request to interconnect 250 MW on the EDE system |
Feasibility Study completed 5/9/05 |
Download |
GEN-2004-018 |
September 15, 2004 |
Request to interconnect up to 800MW on the WFEC System. |
Feasibility Study completed Jan. 25, 2005 ***WITHDRAWN*** |
Download |
GEN-2004-019 |
September 22, 2004 |
Request to interconnect up to 40.5MW on the WFEC system |
Feasibility Study completed March 2005 ***WITHDRAWN*** |
Download |
GEN-2004-020 |
October 08, 2004 |
Request to interconnect up to 36MW on the AEP system **Customer reduced to 27 MW** |
Feasibility Study completed March 2005 |
Download |
GEN-2004-021 |
October 08, 2004 |
Request to interconnect up to 150 MW on the WFEC system |
Feasibility Study completed March 2005 ***WITHDRAWN*** |
Download |
GEN-2004-022 |
October 08, 2004 |
Request to interconnect up to 60 MW on the AEPW system |
Feasibility Study completed March, 8 2005 ***WITHDRAWN*** |
Download |
GEN-2004-024 |
December 13, 2004 |
Request to interconnect 201 MW on the WERE system |
Feasibility Study completed 7/12/05 |
Download |
Please send your requests to GIStudies@spp.org
If you have any questions, please submit a ticket on RMS.
|