OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2002 Facility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2002-006 April 30, 2002 Request to interconnect up to 150MW on the SWPS system. Facility Study completed February 2004 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Facility Study complete Sept. 16, 2004 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Addendum to Facility Study GEN-2002-008 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240 MW on the SWPS system Final Facility Study Completed 4/6/2005 Download
GEN-2002-009 July 19, 2002 Request to interconnect up to 80MW on the SWPS system Facility Study completed 8/3/2004 Download
GEN-2002-019 September 12, 2002 Request to interconnect up to 160 MW on the SWPS system Facility Study Completed February 2005 Download
Gen-2002-022 September 12, 2002 Request to interconnect 240 MW on the SPWS System Facility Study completed October 2005 Download
Gen-2002-025A October 31, 2002 Request to interconnect 150 MW on the WPL System Facility Study completed November 2005 Download
GEN-2002-026 November 13, 2002 Request to interconnect up to 140 MW on the WERE system.(Reduced by Customer to 121 MW) Facility Study completed November 2003 Download

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.