OASIS Apps

- Curtailment Viewer
- DC Tie Viewer
- Price Discounts
- Price Matrix
- Transmission Load Relief

- SPP OASIS Archive Map
    > SPP OASIS Archive Page
    > Market System Status
    > Member Related Postings
    > FERC890 Items

- Studies Postings
 
SPP Logo
 
2002 Feasibility Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2002-001 January 14, 2002 Request to interconnect up to 50MW on the AEPW system Expedited Impact Study Requested (see 2002 Impact Studies) ***WITHDRAWN***  
GEN-2002-002 January 22, 2002 Request to interconnect up to 50MW on the SWPS system Expedited Impact Study Requested (see 2002 Impact Studies)  
GEN-2002-003 February 19, 2002 Request to interconnect up to 120MW on the WERE system Feasibility Study Completed April 2002 ***WITHDRAWN*** Download
GEN-2002-004 April 12, 2002 Request to Interconnect up to 200MW on the WERE system Feasibility Study Completed May 2002 Download
GEN-2002-005 April 28, 2002 Request to interconnect up to 120MW on the WFEC system Feasibility Study Completed May 2002 Download
GEN-2002-006 April 30, 2002 Request to interconnect up to 150MW on the SWPS system Feasibility Study Completed September 2002 Download
GEN-2002-007 May 14, 2002 Request to interconnect up to 1100MW on the SWPS system Feasibility Study Completed December 2002 Download
GEN-2002-008 July 19, 2002 Request to interconnect up to 240MW on the SWPS system Feasibility Study completed December 2002 Download
Gen-2002-008 July 19, 2001 Requet to interconnect up to 240 MW on t he SWPS system Addendum to Gen-2002-008 Download
GEN-2002-009 July 19, 2002 Request to interconnect up to 240MW on the SWPS system Feasibility Study completed December 2002 Download
GEN-2002-010 July 30, 2002 Request to Interconnect up to 240MW on the WFEC system Expedited Impact Study requested (see 2002 Impact Studies) ***WITHDRAWN***  
GEN-2002-011 July 30, 2002 Request to Interconnect up to 160MW on the OKGE system Expedited Impact Study requested (see 2002 Impact Studies) ***WITHDRAWN***  
GEN-2002-012 September 23, 2002 Request to interconnect up to 150MW on the WERE system ***WITHDRAWN***  
GEN-2002-013 September 23, 2002 Request to interconnect up to 200MW on the WERE system Feasibility Study completed December 2002 ***WITHDRAWN*** Download
GEN-2002-014 September 23, 2002 Request to interconnect up to 100MW on the AEPW system ***WITHDRAWN***  
GEN-2002-015 September 23, 2002 Request to interconnect up to 130MW on the AEPW system Feasibility Study completed December 2002 Download
GEN-2002-016 August 12, 2002 Request to interconnect up to 354MW on the AEPW system Expedited Impact Study requested (see 2002 Impact Studies)  
GEN-2002-017 August 14, 2002 Request to interconnect up to 99MW on the WFEC system Feasibility Study completed December 2002 Download
GEN-2002-018 August 23, 2002 Request to interconnect up to 100.8MW on the SWPS system Feasibility Study completed December 2002 Download
GEN-2002-019 September 12, 2002 Request to interconnect up to 160MW on the SWPS system Feasibility Study completed March 2003 Download
GEN-2002-020 September 12, 2002 Request to interconnect up to 75MW on the SWPS system Feasibility Study completed March 2003 ***WITHDRAWN*** Download
GEN-2002-021 September 12, 2002 Request to interconnect up to 160MW on the SWPS system Feasibility Study completed August 2003 ***WITHDRAWN*** Download
GEN-2002-022 September 12, 2002 Request to interconnect up to 240MW on the SWPS system Feasibility Study completed August 2003 Download
GEN-2002-023 September 24, 2002 Request to interconnect up to 150MW on the SWPS system Feasibility Study Completed August 2003 Download
GEN-2002-024 October 25, 2002 Request to interconnect up to 50MW on the WFEC system Expedited Impact Study requested (see 2002 Impact Studies) ***WITHDRAWN***  
GEN-2002-025 October 28, 2002 Request to interconnect up to 40MW on the AEPW system ***WITHDRAWN***  
GEN-2002-026 November 13, 2002 Request to interconnect up to 140MW on the WERE system Expedited Impact Study requested (see 2002 Impact Studies)  

Please send your requests to GIStudies@spp.org

If you have any questions, please submit a ticket on RMS.