GEN-2003-001 |
March 05, 2003 |
Request to interconnect 100.5 MW on the WFEC system |
Feasibility Study completed August 2003 ***WITHDRAWN*** |
Download |
GEN-2003-002 |
March 11, 2003 |
Request to interconnect 200MW on the WERE system |
Feasibility Study completed April 2003 |
Download |
GEN-2003-003 |
May 23, 2003 |
Request to interconnect 80MW on the SWPS system |
***WITHDRAWN*** |
|
GEN-2003-004 |
June 05, 2003 |
Request to interconnect up to 100MW on the WFEC system |
Feasibility Study completed September 2003 |
Download |
GEN-2003-005 |
June 05, 2003 |
Request to interconnect up to 120MW on the WFEC system |
Feasibility Study completed December 2003 |
Download |
GEN-2003-006 |
June 05, 2003 |
Request to Interconnect up to 100MW on the WFEC system |
Feasibility Study Completed December 2003 ***WITHDRAWN*** |
Download |
GEN-2003-007 |
July 14, 2003 |
Request to interconnect 550MW on the EMDE system |
***WITHDRAWN*** |
|
GEN-2003-008 |
July 15, 2003 |
Request to interconnect up to 240MW on the SWPS system |
***WITHDRAWN*** |
|
GEN-2003-009 |
July 16, 2003 |
Request to interconnect up to 81MW on the SWPS system |
Feasibility Study Completed October 2003 ***WITHDRAWN*** |
Download |
GEN-2003-010 |
July 24, 2003 |
Request to interconnect 50MW on the EMDE system |
Feasibility Study Completed January 2004 |
Download |
GEN-2003-011 |
July 24, 2003 |
Request to interconnect up to 600MW on the EMDE system |
***WITHDRAWN*** |
|
GEN-2003-012 |
July 24, 2003 |
Request to interconnect 350MW on the EMDE system |
***WITHDRAWN*** |
|
GEN-2003-013 |
July 29, 2003 |
Request to interconnect up to 198MW on the SWPS system |
Feasibilty Study Completed October 2003 |
Download |
GEN-2003-014 |
July 29, 2003 |
Request to interconnect up to 550MW on the EMDE system |
***WITHDRAWN*** |
|
GEN-2003-015 |
August 06, 2003 |
Request to interconnect 240MW on the SWPS system |
Feasibility Study Completed October 2003 ***WITHDRAWN*** |
Download |
GEN-2003-016 |
October 13, 2003 |
Request to interconnect 100.5MW on the SPS system |
Feasibility Study completed January 2004 ***WITHDRAWN*** |
Download |
GEN-2003-017 |
October 15, 2003 |
Request to interconnect 80 MW on the SPS system |
Feasibility Study completed March 2004 ***WITHDRAWN*** |
Download |
GEN-2003-018 |
October 22, 2003 |
Request to interconnect up to 298.5MW on the SWPS system |
Feasibility Study completed May 2003 |
Download |
GEN-2003-019 |
November 24, 2003 |
Request to interconnect 250 MW of wind generation on the MIDW system. |
Feasibility Study Revised 6/30/04 |
Download |
GEN-2003-019 |
November 24, 2003 |
Request to interconnect 250 MW of wind generation on the MIDW system. |
Feasibility Study Completed 6/25/04 |
Download |
GEN-2003-020 |
December 29, 2003 |
Request to interconnect 240 MW on the SPS system |
Feasibility Study completed March 2004 |
Download |
GEN-2003-021 |
December 29, 2003 |
Request to interconnect 400 MW on the SPS system |
Feasibility Study completed March 2004 ***WITHDRAWN*** |
Download |
GEN-2003-022 |
December 31, 2003 |
Request to interconnect up to 130MW on the AEPW system |
Expedited Impact Study Requested (See 2003 Impact Studies) |
|
GEN-2003-023 |
December 31, 2003 |
Request to interconnect 100 MW in the WERE system |
Feasibility Study Completed 7/28/04 |
Download |
GEN-2003-023 |
December 31, 2003 |
Request to interconnect 100 MW in the WERE system |
Revised Feasibility Study Completeed 8/5/04 |
Download |
GEN-2003-024 |
December 31, 2003 |
Request to interconnect up to 201MW on the WERE system |
Feasibility Study Completed 8/19/04 |
Download |