2005 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
Gen-2005-002 January 18, 2005 Request to interconnect 80 MW on the SWPS System Impact Study completed September '05 Download
Gen-2005-003 January 21, 2005 Request to interconnect 30.6 MW on the WFEC System Expedited Impact Study completed August 2005 Download
Gen-2005-005 March 22, 2005 Request to interconnect 18 MW on the OKGE System Impact Study completed November 2005 Download
Gen-2005-006 March 22, 2005 Request to interconnect 150 MW on the OKGE System. Impact Study completed November 2005 Download
Gen-2005-007 March 23, 2005 Request to interconnect 260 MW on the SWPS system Impact Study completed January 2006 Download
Gen-2005-008 April 01, 2005 Request to interconnect 130.5 MW on the OKGE system Impact Study completed January 2006 Download
Gen-2005-010 July 28, 2005 Request to interconnect 232.5 MW on the SWPS system Impact Study completed January 2006 Download
GEN-2005-012 August 08, 2005 Request to interconnect 400MW on the WEPL system Impact Study completed July 2006 Download
Gen-2005-012 August 08, 2005 Request to interconnect 400MW on the WEPL System Impact Study re-studied January 2007 Download
Gen-2005-012 August 08, 2005 Request to interconnect 400MW on the WEPL System Impact Re-Study completed November 2007 Download
Gen-2005-012 August 08, 2005 Request to interconnect 400MW on the WPEK system Impact Re-Study completed June 2008 Download
GEN-2005-012 August 02, 2005 Request to interconnect 248.4MW on the SUNC transmission system Posted Restudy 3/9/2011 Download
GEN-2005-013 August 22, 2005 Interconnect 201 MW on the Westar transmission system Impact Restudy posted 3/19/2010 Download
GEN-2005-013 August 22, 2005 Addendum to Impact Restudy Study completed May 2010 Download
Gen-2005-013 August 22, 2005 Request to interconnect 201 MW on the WERE system Impact Study Completed February 2006 Download
Gen-2005-015 September 14, 2005 Request to interconnect 150MW on the SWPS system Impact Study completed April 2006 Download
Gen-2005-016 September 14, 2005 Request to interconnecct 150MW on the WERE system Impact Study completed November 2006 Download
Gen-2005-017 September 26, 2005 Request to interconnect 340MW on the SWPS system Impact Study completed January 2007 Download
Gen-2005-017 September 26, 2005 Request to interconnect 340MW on the SWPS system Impact Re-Study completed November 2007 Download
Gen-2005-021 October 24, 2005 Request to interconnect 150MW on the SWPS system Impact Study completed September 2006 Download
Gen-2005-022 December 13, 2005 Request to interconnect 168MW on the AEP System Impact Study completed July 2006 Download
Gen-2005-024 December 13, 2005 Request to interconnect 172MW on the AEPW system Impact Study completed August 2006 Download