The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
GEN-2005-001 January 13, 2005 Request to interconnect up to 201 MW on the KCPL System Feasibility Study completed 7/19/05 Download
GEN-2005-002 January 18, 2005 Request to interconnect 80MW on the SPS system Feasibility Study completed May 6, 2005 Download
GEN-2005-003 January 21, 2005 Request to interconnect up to 30.6 MW on the WFEC System Expedited Impact Study Requested  
GEN-2005-004 February 16, 2005 Request to interconnect up to 250 MW on the SWPS System Feasibility Study Completed 5/15/05 Download
GEN-2005-005 March 22, 2005 Request to interconnect up to 18 MW on the OKGE System Feasibility Study Completed 5/13/05 Download
GEN-2005-006 March 22, 2005 Request to interconnect 150MW on the OKGE system Feasibility Study completed 6/13/05 Download
GEN-2005-007 March 23, 2005 Request to interconnect 260 MW on the SWPS system Feasibility Study requested 3/23/05 Download
GEN-2005-008 April 01, 2005 Request to interconnect 130.5 MW on the OKGE System Feasibility Study completed 9/8/05 Download
GEN-2005-009 April 25, 2005 Request to interconnect 150 MW on the OKGE System Feasibility Study completed 9/27/05 Download
Gen-2005-009A May 31, 2005 Request to interconnect 200 MW on the WEPL System Feasibility Study completed 11/18/05 Download
GEN-2005-010 July 28, 2005 Request to interconnect 232.5 MW on the SWPS System Feasibility Study completed 9/26/05 Download
Gen-2005-011 August 02, 2005 Request to interconnect 160 MW on the SWPS System Feasibility Study completed November 17, 2005 Download
Gen-2005-012 August 08, 2005 Request to interconnect 400MW on the WEPL system Feasibility Study completed 3/17/06 Download
Gen-2005-013 August 22, 2005 Request to interconnect 201 MW on the WERE System Feasibility Study completed November 23, 2005 Download
Gen-2005-014 August 22, 2005 Request to interconnect 201 MW on the KCPL System Feasibility Study completed December 12, 2005 Download
Gen-2005-015 September 14, 2005 Request to interconnect 150 MW on the SWPS System Feasibility Study completed December 16, 2005 Download
Gen-2005-016 September 14, 2005 Request to interconnect 150MW on the WERE system Feasibility Study posted April 24, 2006 Download
Gen-2005-017 September 26, 2005 Request to interconnect 340MW on the SWPS system. Feasibility Study completed 3/7/05 Download
Gen-2005-018 September 29, 2005 Request to interconnect 32MW on the OKGE system Feasibility Study completed April 21, 2006 Download
Gen-2005-019 September 29, 2005 Request to interconnect 32MW on the OKGE system Feasibility Study completed April 21, 2006 Download
Gen-2005-021 October 24, 2005 Request to interconnect 150MW on the SWPS systesm Feasibility Study completed May 4, 2006 Download
Gen-2005-022 December 13, 2005 Request to interconnect 168MW on the AEP system Feasibility Study completed May 18, 2006 Download
Gen-2005-024 December 13, 2005 Request to interconnect 172MW on the AEP system Feasibility Study completed May 18, 2006 Download