2000 Impact Studies |
The following Generator Interconnection Studies have been requested.
|
Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
GEN-2000-007 |
September 25, 2000 |
Request to interconnect 550MW on the AEP West transmission system |
Withdrawn (Completed Impact Study March 2001) |
Download |
GEN-2000-008 |
September 25, 2000 |
Request to interconnect 550MW on the KCPL transmission system |
Completed Impact Study March 2001 |
Download |
GEN-2000-015 |
December 20, 2000 |
Request to interconnect 180VW on the Western Farmers transmission system |
Impact Study completed August 2001 |
Download |