Study Number |
Date Requested |
Purpose of Study |
Remarks |
Report |
GEN-2000-003 |
July 13, 2000 |
Request to interconnect 280MW on the SPS transmission system |
Withdrawn (Completed Feasibility Study - Sep. 2000) |
Download |
GEN-2000-004 |
August 16, 2000 |
Request to interconnect 800MW on the AEP West transmission system |
Withdrawn (Completed Feasibility Study - Oct. 2000) |
Download |
GEN-2000-009 |
October 02, 2000 |
Request to interconnect 500MW on the AEP West transmission system |
Withdrawn (Feasibility Study complete - Oct. 2000) |
Download |
GEN-2000-010 |
October 25, 2000 |
Request to interconnect 400MW on the AEP West transmission system |
Withdrawn (Feasibility Study complete January 2001) |
Download |
Please send your requests to GIStudies@spp.org