2013 Impact Studies
The following Generator Interconnection Studies have been requested.

Study Number Date Requested Purpose of Study Remarks Report
January 01, 1900  
ASGI-2013-001 LOIS February 15, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 7/31/2013 Download
ASGI-2013-004 March 07, 2014 Modification Request to interconnect 36.6 MW on the SUNC transmission system Posted 4/10/2014 Download
ASGI-2013-004 LOIS November 06, 2013 Limited Operation Impact Study for Generation Interconnection Study Posted 12/9/2013 Download
DISIS-2013-001 March 31, 2013 Definitive Interconnection System Impact Study DISIS-2013-001 Posted 7/31/2013 Download
DISIS-2013-001-1 March 31, 2013 Definitive Interconnection System Impact ReStudy DISIS-2013-001-1 Posted 8/30/2013 Download
DISIS-2013-001-2 March 31, 2013 Definitive Interconnection System Impact ReStudy DISIS-2013-001-2 Posted 1/31/2014 Download
DISIS-2013-001-3 March 31, 2013 Definitive Interconnection System Impact ReStudy DISIS-2013-001-3 Posted 7/30/2014 Download
DISIS-2013-001-4 March 31, 2013 Definitive Interconnection System Impact Restudy DISIS-2013-001-4 Posted 10/23/2014 Download
DISIS-2013-002 September 30, 2013 Definitive Interconnection System Impact Study DISIS-2013-002 Posted 1/31/2014 Download
DISIS-2013-002-1 September 30, 2013 Definitive Interconnection System Impact Restudy DISIS-2013-002-1 Posted 7/31/2014 Download
DISIS-2013-002-2 September 30, 2013 Definitive Interconnection System Impact Restudy DISIS-2013-002-2 Posted 10/23/2014 Download
GEN-2013-002 September 27, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 9/25/2014 Download
GEN-2013-008 September 27, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 10/8/2013 Download
GEN-2013-014 October 13, 2014 Modification Request to interconnect 25.5 MW on the NPPD transmission system Posted 11/19/2014 Download
GEN-2013-019 September 27, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 9/25/2014 Download
GEN-2013-029 January 14, 2015 Impact Restudy for Generator Modification (Turbine Change) Posted 2/27/2015 Download
GEN-2013-032 September 27, 2013 Limited Operation Impact Study for Generation Interconnection Request Posted 4/8/15 Download
PISIS-2013-001 June 30, 2013 Preliminary Interconnection System Impact Study PISIS-2013-001 Posted 8/30/2013 Download
PISIS-2013-002 June 30, 2013 Preliminary Interconnection System Impact Study Posted 2/28/2014 Download

Please send your requests to GIStudies@spp.org